QUOTATION

ICF Form Supply
Project:Interactive Demo — Demonstration House
Date:27 October 2026
Selected all-level ICF wall area:256.1 m²
Valid For:30 days

From (Contractor)

To (Client) — edit in Project Settings →

3D view of the job

3D model view, not to scale.

Quoted wall scope — Foundations + Ground Floor

Foundation wall forms are listed as their own section. Exterior wall forms and any ICF internal wall forms are itemised for each building level, followed by any selected bracing and other project-wide items.

Wall lengths: priced at block-friendly sizes, each wall adjusted to whole Nudura modules.

Scope of Works

Supply of the itemised ICF wall system.

Foundation ICF wall forms are included as their own itemised section. Foundation footings are excluded.

Not in this quote: Top of Wall.

Price breakdown

Foundation ICF wall forms are shown first, then each building level. Selected project-wide items follow the wall-form subtotal.

DescriptionQtyUnitRateAmount
Foundations
Foundation ICF wall forms — 152mm core
Quantity includes 63.61 m² installed plus 11.17 m² cut off (offcuts that cannot be reused) and 0.77 m² of part forms left over (usually used or kept). Foundation footings are excluded.
75.55 m² $175.00 $13,221.25
Ground Floor
External ICF wall forms — 152mm core
Area-priced form/block package. Block counts are available on request.
136.48 m² $175.00 $23,884.00
Internal ICF wall forms — 102mm core
Area-priced form/block package. Block counts are available on request.
57.29 m² $175.00 $10,025.75
ICF wall-form supply subtotal$47,131.00
Bracing & Hire
Wall bracing hire allowance
Estimated hire allowance based on the brace quantity and hire duration shown. The final charge is adjusted to actual site use and reduced pro rata if fewer braces are used or the hire period is shorter.
103 ea $40.00 $4,120.00
Scaffold Planks (5 days)
$5.00/day × 5 days = $25.00 each.
66 ea $25.00 $1,650.00
Temporary Handrail Material
185.9 m $12.00 $2,230.80
Freight / Delivery
Freight / delivery
Project-wide allowance: number of freight trips × delivery rate per trip.
0 trip $250.00 $0.00
Other ICF Parts
Formlock
60 pcs $3.50 $210.00
Vertical Joint Clips
528 pcs $0.80 $422.40
ICF Screws
Reusable across pours: 1,060 screws is the largest single-stage requirement, supplied as 3 whole 500-piece boxes.
3 box $45.00 $135.00
Opening Treatments
Timber Head, Jamb & Sill (152×45mm, inserted)
92.7 m $19.85 $1,839.30
Internal: Timber Head & Jamb (102×45mm, inserted)
29.2 m $18.85 $551.17
Concrete
External walls ready-mix concrete — 25 MPa (Design Assist basis)
25 MPa is the accepted structural wall basis used by this metadata-free Design Assist project. Current wall checks still require their ordinary review.
19.7 m³ $300.00 $5,919.00
Internal walls ready-mix concrete — 25 MPa (Design Assist basis)
25 MPa is the accepted structural wall basis used by this metadata-free Design Assist project. Current wall checks still require their ordinary review.
5.6 m³ $300.00 $1,668.00
Foundation ready-mix concrete — 25 MPa (Design Assist basis)
25 MPa is the accepted structural wall basis used by this metadata-free Design Assist project. Current wall checks still require their ordinary review.
9.7 m³ $300.00 $2,901.00
Concrete Pump
35.0 m³ $45.00 $1,573.20
Concrete Practical Allowances
Pump Callout Fee (Foundation)
1 ea $350.00 $350.00
Pump Callout Fee (External Walls, pro-rata)
0.8 share $350.00 $273.00
Pump Callout Fee (Internal Walls, pro-rata)
0.2 share $350.00 $77.00
Reinforcing Steel
External Walls: Reinforcing steel, cut and bent
H10: 1154.348 m / 711.699 kg; H16: 106.295 m / 167.769 kg W11: steel from an earlier engine run; the engine no longer offers a design for this wall. Reinforcing steel, cut and bent, all bars. PHD price (Jeremy Chisholm), 16 Oct 2026.
879.5 kg $3.60 $3,166.09
Internal Walls: Reinforcing steel, cut and bent
H10: 573.599 m / 353.645 kg I1, I2, I5: minimum steel to NZS 3101; loads from above and bracing not assessed. I3, I4: not designed; an allowance at the minimum steel (bars need to be closer than the block's seats). Reinforcing steel, cut and bent, all bars. PHD price (Jeremy Chisholm), 16 Oct 2026.
353.6 kg $3.60 $1,273.12
Foundation walls: Reinforcing steel, cut and bent
H10: 922.693 m / 568.875 kg Reinforcing steel, cut and bent, all bars. PHD price (Jeremy Chisholm), 16 Oct 2026.
568.9 kg $3.60 $2,047.95
Beam and lintel reinforcing steel
2 lintels have no steel here: the engine withheld a design. 3 lintels: design withheld: load not known; minimum wall-steel detail counted, not a design.
301.4 kg $3.60 $1,085.04
Consumables Allowance
Consumables Allowance (see included items)
Includes foam adhesive, joint tape, waterproofing/sealants, penetration sealing, temporary bracing fixings, fasteners and screws, and miscellaneous site consumables.
0 allowance $0.00 $0.00

ICF form supply quantities are the whole forms supplied, including unavoidable product rounding and non-reusable offcuts. Reusable offcuts of at least half-course height are credited by the quantity calculation. Detailed block counts remain in the contractor records. Foundation footings are not included.

Pricing Basis

Pricing basis: none of the rates behind this quote have been confirmed for this project yet. Check prices before issuing.

Subtotal$78,623.07
Quote total — selected contractor scope$78,623.07
GST (15.0%)$11,793.46
TOTAL (incl. GST)$90,416.53

Inclusions

Exclusions

Assumptions

Engineering Notes

Footing steps rationalised to runs of 2 m or more; the deeper level adopted (builder's practice).

Optional Extras

Optional scope is already included or will be quoted separately on request.

Payment Terms

100%One invoice for the total quote amount, due at the time of supply.

Availability

Credentials

Price Hold & Conditions

Price held for 30 days from the date of issue.

All prices are exclusive of GST unless stated otherwise.

Quantities are based on the ICF wall design and may vary with site conditions.

Variations to scope will be quoted separately.

Estimated hire allowance based on the brace quantity and hire duration shown. The final charge is adjusted to actual site use and reduced pro rata if fewer braces are used or the hire period is shorter.

Contractor Signature / Date